The first element of the Fehmarn Belt Tunnel between Germany and Denmark could be lowered off the Danish island of Lolland as early as this spring, Danish state-owned construction company Sund & Bælt said on Thursday.
A special vessel that is to sink the tunnel elements has been approved by the Danish Maritime Authority, the company said.
The ship's task was "complex, so numerous tests were necessary," deputy contract director Lasse Vester said in the statement. "Now we have received approval for the ship and can start lowering it."
The construction consortium Femern Link Contractors (FLC) can now begin the necessary preparations, it said.
In January, Sund & Bælt said the opening of the 18-kilometre tunnel was likely to be delayed until 2031, partly because of missing permits. Once the first tunnel elements have been sunk, a new timetable will be drawn up, it had now said.
Huge infrastructure project
According to Sund & Bælt, the Fehmarnbelt Tunnel for cars and trains is one of Europe's largest infrastructure projects. It will eventually connect the German island of Fehmarn with the Danish island of Lolland.
On the German side, a hinterland connection is being built that also includes the Fehmarn Sound Tunnel between the island and the German mainland.
Sweet Taste? Candy Fulfills You
Porsche May Kill the Electric Boxster Before It Ever Arrives
Woman charged in unprovoked stabbing of tourist changing baby's diaper in Macy’s Herald Square store
Nations for Rock Climbing
6 Popular Men's Aromas On the planet
Remarkable Spots for Hot Air Swelling All over The Planet
Iran War Derails The Automotive Industry
Best Wellness Tracker Keep You On target
UN torture cm'tee report flags Israel for allegedly mistreating journalists, detainees, ex-MAG